Spill remediation update:
We're most of the way through a second work day. I'd say at this rate there is about one more day to go. There was a team of four on site yesterday and again this morning.
A lot of today has been one guy with a backhoe and a tip truck, chipping away at the task of removing a fuckton* soil.
*about 14 ton so far